Hi,
I’m currently trying to synchronize between SOLMAN to ARIS for Sap BA 7.02.
I have encountered the following error during synchronization:
‘WARNING: Unable to include the 'Process step Manage ----' item.
Either the item has to be moved, and source and target are not part of the synchronization. In this case, start synchronization from a superior structural element to which source and target must be subordinate.
Or the occurrence of this item has been deleted without deleting the corresponding definition. Delete the 'SAP ID' attribute from the definition and restart the procedure.’
Pl. suggest a resolution for this types of error messages.
hi,
this warning is shown if the synchronization wants to move an item in ARIS but the source item which should be moved to the new position was not found.
two reasons for that could exist
A: the node to which the source belongs is not part of the synchronization. you can avoid this by starting the synch on the project root node or any common parent node of move source and move target.
B: the source does not exist anywhere as occurence in your project. In that case just search for that item in the ARIS database and delete it if you have no other use for it or just delete the SAP ID attribute for this item. then the item is not recognized as synchronization relevant and is ignored completely.
hope this helps