Anais.Cisneros's picture

Dear all,

I am writing to get some advice regarding what the best practice is to model risk. Currently, I am using an EPC to diagram the process, and I add FADs to the activities to showcase the associations

 

As you can see in the FAD diagram I was able to add a cause to a risk, but I am not sure how do associate several causes to the same risk.

After doing some research I found that ARIS 7.2 has a new risk modeling called the Bow tie methodology, an example is shown here:

However, I am not sure how to connect the Bow tie Diagram with the FAD, and I am wondering if there are other ways to solve my initial problem (adding several causes to a risk).

I hope you can give me some advice regarding what to do, or tell me where to search.

 

Kind regards,

Anais

Tags: ARIS risk