Profile picture for user Eva Klein

Compared to actual processes (as-is), target processes (to-be) are usually expected to bring about improvements in terms of cost and time. For example, an improved process should cost less and its execution should be faster.

Improvement potential can be identified using the "Analyze times/costs" standard report included in ARIS. This report enables you to compare planned improvements with the given times and costs of the current business reality. For this purpose, specific information has to be specified in the process model, such as the duration of a process step, for example. The analysis can be performed for a single process or for multiple processes. This way you can easily determine which of the relevant process steps generate high costs or require long processing times (also including wait times).

Time attributes

  • Min. processing time, Avg. processing time, Max. processing time

    These attributes specify the duration of time that may elapse between start time and end time of a task.
  • Min. orientation time, Avg. orientation time, Max. orientation time

    These attributes specify the orientation times required for a function or resource based on the last simulation run.
  • Min. wait time, Avg. wait time, Max. wait time

    These attributes specify the wait time accrued for process folders at a rule.
  • Frequency, daily / Frequency, weekly / Frequency, monthly / Frequency, annually

    These attributes determine the equally distributed frequency/quantity with which an object is activated or occurs within a specific period of time (day, week, month, year) in the process in question. This event attribute is evaluated by the simulation.

The total time for carrying out a function one time should sum up the processing time and the orientation time, excluding the wait time. The time per day is calculated based on the time, frequency, and weighting factor of the organizational unit.

Cost attributes

  • Min. total costs, Avg. total costs, Max. total costs

    Attribute types for recording costs incurred by the object under consideration.
  • Min. material costs, Avg. material costs, Max. material costs

    Attribute types for recording costs that are directly associated with the processing and use of materials within the company.
  • Min. personnel costs, Avg. personnel costs, Max. personnel costs

    Attribute types for recording costs incurred by human resource management.
  • Min. energy costs, Avg. energy costs, Max. energy costs                     

    Attribute types for recording costs that are directly associated with energy usage.
  • Min. operating supplies costs, Avg. operating supplies costs, Max. operating supplies costs

    Attribute types for recording costs that are directly associated with operating supplies.
  • Min. various overhead costs, Avg. various overhead costs, Max. various overhead costs

    Attribute types for recording costs that cannot be clearly allocated to a cost area.
  • Min. costs for depreciation/repair/maintenance, Avg. costs for depreciation/repair/maintenance, Max. costs for depreciation/repair/maintenance

    Attribute types for recording costs that are directly associated with depreciation and maintenance.
  • Min. imputed interest, Avg. imputed interest, Max. imputed interest

    Attribute types for recording costs that are estimated to be the internal interest for an object.
  • Min. other costs, Avg. other costs, Max. other costs

    Attribute types for recording costs that cannot clearly be allocated to a cost area in the Costs attribute type group.

The total costs for carrying out a function one time should sum up all costs. The costs per day are calculated based on costs and frequency.

How to start the report

The "Analyze times/costs" report provided by ARIS can be run for the following model types:

  • EPC
  • Industrial process
  • Office process
  • UML Activity diagram
  • PCD
  • VACD

Report dialog

After the report was started, a dialog opens providing various evaluation options. You can choose to analyze either times or costs, and you can define the output of the values (minimum, average, or maximum value).

Example of cost evaluation

Lists all functions of a process and outputs the attribute values for the costs.

The output shows the costs for functions that are carried out once and the costs for individual functions per day.

The function costs per day are calculated based on the frequency you specify (e.g. number of function executions per day).

Example of time evaluation

Lists all functions of a process and outputs the attribute values for the times.

You can select different time units for the calculation:

The Excel sheet will provide the following output:

The output shows the times for functions that are carried out once and the times required by the relevant functions per day.

The times required per day are calculated based on the frequency you specify (e.g. number of function executions per day).

Due to the "Analyze times/costs" report you will gain an overview of process steps that involve high costs and take a great amount of time.

Optimization potential can be determined in greater detail using ARIS Business Optimizer. You can also use this product for the measurement of improvement results during and after the implementation process. I will provide further information on ARIS Business Optimizer in a future article.

by Ismael Shameem Etowar
Posted on Wed, 01/19/2011 - 06:11

Dear Ms Klein,

 

Thank you very much for this post.

I was struggling with this report for a while now.

Thanks for everything, you are the BEST :).

 

Cheers

 

Shameem

0
by Eva Klein
Badge for 'Community Team' achievement
Author
Posted on Wed, 01/19/2011 - 07:51

Hi Shameem,

thanks a lot for your feedback, I try my best ;-)!

I'm happy if I can help you with my posts.

Best regards

Eva

0
by Bob Langan
Posted on Wed, 01/19/2011 - 20:43

Thank you for this posting.  It is a great summary.  We plan to use this for process improvement initiatives.   Question - how are the attributes enabled so I can start populating time cost data?   I checked various websites and manuals/book, plus some trial&error.  Any additional detail is appreciated.

0
by Eva Klein
Badge for 'Community Team' achievement
Author
Posted on Tue, 01/25/2011 - 13:25

Hi Bob,

mark the function you want to specify and click the "More attributes"-button in the Properties dialog. In the Insert attributes dialog you will find the times and costs folder. Select the time and cost attributes you want to define, click "OK" and then you can enter your values in the Properties dialog. 

Regards

Eva

0
by Gopal Chimnani
Posted on Tue, 01/25/2011 - 17:56

Hi Eva,

Thanks for wiriting the detailed approach for running this report. I believe the actual world is not that simple ..  It would be good if communitiy discusses and comes out with the approach to use this report considering following challenges.  

1. Data Collection : Simple model to calculate the activity / unit cost, Activity based costing is one of the approach, but then simple ARIS process attributes are not geared to handle Cost Drivers / Resource Driver related parameters. Even Activity Based Add on Module need to improve little to enable ABM.

2. Data upload : Templates as documented above,but that can be directly imported  into ARIS using Tranlation IN/Translation Out reports

3. Attributes : Any process to calculate total cost /lead time would need following attributes

    -  decision making,hence process paths, hence probabilities.

    -  Assignments : hence sub process details, sub process cost/lead  for aggregation

    - Interfaces : hence delays and wait time from connected processes

    - Roles : hence resources, their availability, FTE information and probabilities of they on holidays

    - Applications : Maintenance and Downtime n their respective parameters

    - Process Exceptions : Emergencies e.g. in Project management processes.

 4.    Scenarios : Selection of specific situation

5. Report execution

Thanks

regards

Gopal

0
by Sadiq AL-Shara
Posted on Wed, 04/04/2012 - 01:24

Hi Eva,

Thank you for the informative post as always.

I am facing one small dilemma with the report and am not sure if it can be solved:

Usually, EPCs would contain process interfaces, which technically represent a higher level than the EPCs they are in, which would also mean that their maintained time/costs attribute(s) are of higher level also.

Now when running the report, the time and costs of interfaces are taken into consideration when they should not be, so is there any way to avoid that?

0
by Pieter Beerten
Posted on Mon, 05/14/2012 - 02:29

I know this is a dummy question, but can somebody briefly explain me what this 'orientation time' is?

thank you in advance!

0
by Elaine Wrobel
Posted on Mon, 06/11/2012 - 03:43

Hi Pieter,

I use orientation time to indicate the time required for someone to explain the activity. For example, a function like "Compile Contract Information" may require the Supervisor to tell the Analyst how to compile the contract information, and the Analyst cannot proceed with the activity without this orientation from his/her Supervisor.

Does that make sense to you? That's how I've been using this attribute.

Regards,

Elaine.

0
by Raghav Mathur
Posted on Tue, 05/13/2014 - 19:35

Hi,

I am new to this forum and community but I am interested in exploring this option of calculating process time/cost.

Please can you tell me from where exactly can I access this feature of "Analyze times/costs" report?

I downloaded the free ARIS Express but that does not seem to have any report functionality.

Many thanks.

0
by Eva Klein
Badge for 'Community Team' achievement
Author
Posted on Thu, 05/15/2014 - 14:43

Dear Raghav,

ARIS Express doesn't support the execution of reports. If you want to execute this report you need the full version of ARIS.

Here, you can find a detailed comparison of our products Process Live, ARIS Express and ARIS 9.

Regards

Eva

0
by Raghav Mathur
Posted on Tue, 05/27/2014 - 01:50

Hi Eva, thanks a lot for your response. The link you provided was quite helpful.

Also, by full version of ARIS, are you referring to ARIS 9?

Although I was able to get a free trial version of Process Live but I could not find a way to get a trial version for ARIS 9.

Please could you provide the link from where I can get a trial version of ARIS 9?

Many thanks.

Raghav

 

0

Featured achievement

Question Solver
Share your expertise and have your answer accepted as best reply.
Recent Unlocks
  • CP
  • BZ
  • Profile picture for user TEF_Bernd
  • ПЦ
  • CR
  • PacMan

Leaderboard

|
icon-arrow-down icon-arrow-cerulean-left icon-arrow-cerulean-right icon-arrow-down icon-arrow-left icon-arrow-right icon-arrow icon-back icon-close icon-comments icon-correct-answer icon-tick icon-download icon-facebook icon-flag icon-google-plus icon-hamburger icon-in icon-info icon-instagram icon-login-true icon-login icon-mail-notification icon-mail icon-mortarboard icon-newsletter icon-notification icon-pinterest icon-plus icon-rss icon-search icon-share icon-shield icon-snapchat icon-star icon-tutorials icon-twitter icon-universities icon-videos icon-views icon-whatsapp icon-xing icon-youtube icon-jobs icon-heart icon-heart2 aris-express bpm-glossary help-intro help-design Process_Mining_Icon help-publishing help-administration help-dashboarding help-archive help-risk icon-knowledge icon-question icon-events icon-message icon-more icon-pencil forum-icon icon-lock