Hi,
we are facing some problems with Solution Manager synchronization after made the upgrade of ARIS from 7.2 to 9.6.
We have two SAP Solution Manager one SDX (sandbox) and another one that is the SMD (DEV) on project on ARIS 7,2 could synchronize with both SAP Solution Manager but after we export this project from 7.2 and import into 9,6, the synchronization only is possible in SDX that is the Solman that we created the project .
PS. We create projects in SDX and transport to SMD through request.
The erro shows like we do not have valid configurations.
does anyone resolved this error?
Thanks,
Marcus Campos