I am trying to fix a broken SAP project structure. After reconnecting my EPC Process Model to the SAP Process function on the Scenario model and reconnecting the scenario model to the SAP VACD function contained on the Project Model which is connected to the project root function I receive the following error.
"Unable to determine the logical components. Please check whether the assignment relationships between the project element and this model are maintained consistently."
This is a very inconsistant problem. Some scenarios I fixed are structurally sound, but others receive the above error. I am at a lost in finding the common reason for receiving the above error.
If anyone can provide any insight or guidance to isolate the problem it would be GREATLY appreciated.
Thanks very much,
Mike
Sascha Ding on
Hi Mike,
it seems that the assignment structure of your SolMan project is inconsistent.
For example a scenario model has maintained the process 'PR1_1' but the process has no assignment to its process model 'PR1_1'. And if you then try to sync one of the process steps (e.g. PRS1_1_1) of this process 'PR1_1' then the synchronisation can not find the project root node (e.g. to get the system landscape). In Other words there is anywhere a broken relationship from any structure element to the project root in your SolMan project
Best regards,
Sascha