Hello community!
I've a doubt regarding ARIS sync SOLMAN:
The processes flows designed in ARIS can be synchronized to SOLMAN? In other words, when started sync ARIS to SOLMAN, beyond the structure of branches/scenarios/process/steps, will the flows also be synchronized?
If it'll be possible, Can I use EPC diagram or BPMN only?
Tks in advanced
Tiago Cassiano
Roy de Vries on
Hi Tiago,
Both is possible. There are 2 guides that help you perform the needed configuration.
https://blogs.sap.com/2018/03/23/aris-integration-with-sap-solution-manager-7.2-part-1/
https://blogs.sap.com/2018/03/27/aris-and-sap-solution-manager-7.2-integration-part-2/
Hope this helps.